Today the Electricians arrived to begin work on the shed. Its an exciting prospect given it has been about 10 months in the planning. The current plans should have enough power and flexibility to future proof the shed.

Details
  • New 32A three phase sub-main, from the location of the existing meter box to the RH rear of the residence, then underground to the approx.. center of the proposed work shop area.
  • 12 pole D.B in the proposed new workshop, c/w main switch and ELCB,s for light and power circuits. 
  • Twenty One (21) batten holders (16 – in the workshop, 4 in the storage area and 1 in the carport.) LED lamps to be supplied by owner.
  • One light switch for the workshop, one light switch for the Storage Area & one weatherproof light switch for the carport, and one 2 gang switch for the ceiling mount GPO’s.
  • One double weatherproof power point in the Carport.
  • Two ceiling mount double 10amp power points.
  • Four 10amp double power points.
  • Four single 15Amp 240volt power points in the workshop.
  • One double 15Amp power point.
  • One three phase 10A power outlet.
Re: Ray's question. The sub main is on the right hand side inside the door where the switches will be easy to reach. The scrap bin is easy to reach across at that point, but I may yet move it.